Project overview

Complete full depth road reconstruction of Sherwood Crescent including removal and installation of sanitary and storm sewers, and watermains complete with connection to 45 existing services.

South_Huron_logo
b3lineicon|b3icon-map-location||Map Location

LOCATION

Sherwood Crescent
Exeter Ontario

b3lineicon|b3icon-file-text||File Text

SCOPE

  • Sanitary sewers (200mm and 250mm dia.) 620m 
  • Storm sewers (300 to 525mm dia.) 630m
  • Watermain (150mm dia.) 635m
  • Complete road reconstruction 620m
  • Granular Base 9750 tonnes
  • Base and Surface Asphalt 1455 tonnes
  • Curb Construction 1395m
  • Import topsoil and sod 5500m2
b3lineicon|b3icon-university||University

VALUE

2,000,000