Another ghn Group Project
Deerhaven SWMF Sediment Removal
Project Owner: Corporation of Middlesex Centre
—
Project overview
Install erosion and sediment controls, dewatering of the stormwater management facility (SWMF) with the implementation of inflow bypass controls, liase with Environmental Inspector to relocate fish, amphibian and widlife as per Ministry of Natural Resources and Forestry (MNRF) guidlines, removal of sedment from the forebay and main cell including disposal at an Ministry of Environment, Conservation and Parks (MECP) Licensed landfill, restoration of landscape areas.
LOCATION
Meredith Drive
Ilderton, Ontario
SCOPE
- Excavate and dispose of 2500m3 of contaminated pond sediment at an approved MECP Licensed Landfill
- Removal of invasive phragmites and voluntary woody brush along the perimeter of the SWM Pond
- Restoration of 5000m2 of sod areas with imported screened topsoil and hydroseed
VALUE
550,000