Project overview
Strip and stockpile 30000m3 of topsoil and complete onsite cut to fill of 60000m3 including construction of a SWM Pond with storm inlets and outlets.
LOCATION
70 Church Street
Exeter, Ontario
SCOPE
- Strip and stockpile onsite 30000m3
- Onsite cut to fill 60000m3
- Storm Sewers (200 to 1050mm dia.) 235m – SWM Pond Facility construction
- Granular Base 3000 tonnes
- Surface asphalt 150 tonnes
VALUE
1,100,000