Another ghn Group Project
2020 Pond Restoration & Sediment Removal
Project Owner: The Corporation of the City of Guelph
—
Project overview
Install erosion and sediment controls for the City’s SWM Facility 10 and 93, dewatering of SWM Facilities with the implementation of inflow bypass controls, liase with Environmental Inspector to relocate fish, amphibian and widlife as per Ministry of Natural Resources and Forestry (MNRF) guidlines, removal of sedment from each ponds forebay and main cell including disposal at an Ministry of Environment, Conservation and Parks (MECP) Licensed landfill.
LOCATION
687 Edinburgh Road South
78 Ingram Drive
Guelph, Ontario
SCOPE
- Excavate and dispose of 5000m3 of contaminated pond sediment at an approved MECP Licensed Landfill
- Removal of voluntary woody brush along the perimeter of the SWM Pond
VALUE
1,100,000